Connect with us

Community

MassDOT issues update on South Coast Rail work in Fall River, New Bedford, area towns

Published

on

MassDOT has issued an update on South Coast Rail work taking place in southern New England.

Assonet: Detour for Grade Crossing, Culvert and Track Work at Beechwood Road

Location of Work: Railroad grade crossing at Beechwood Road in Assonet

Dates/Hours of Work: Detour currently in place and continues to Sunday, October 3; final paving of road Saturday, October 2, 7:00 PM to 1:00 AM; all other days, regular work hours are 7:00 AM to 7:00 PM

Beechwood Road in Assonet will be closed to all vehicular and pedestrian traffic until Sunday, October 3. All through traffic will be routed to Richmond Road/Route 79 and Malbone Road in Assonet. Police details will allow local traffic access only on Beechwood Road.

Lakeville: Detour for Grade Crossing Work at Leonard Street

Location of Work: Leonard Street in Lakeville

Dates/Hours of Work: 24-hours/day Friday, September 24 to Sunday, September 26

Leonard Street in Lakeville will be closed to all vehicular and pedestrian traffic beginning Friday, September 24 to Sunday, September 26. All through traffic will be routed to Taunton Street, North Precinct Street and Southworth Street in Lakeville. Police details will allow local traffic access only on Leonard Street.

Assonet: 24-Hours/Day Track Work

Location of Work: Railroad right-of-way between Colonial Drive and Forge Road in Assonet

Dates/Hours of Work: 24-hours/day Wednesday, September 29 to Sunday, October 3

Daytime Work on Middleborough Secondary and New Bedford Main Line

Location of Work: •New Middleborough Station site, 161 South Main Street, Middleborough •East Taunton Station site, 1141 County Street, Taunton •Wamsutta Layover Facility site, 217 Herman Melville Boulevard, New Bedford •Church Street Station site, 387 Church Street, New Bedford •Middleborough Secondary and New Bedford Main Line right-of-way

Dates/Hours of Work: •Monday, September 20 through Sunday, September 26, 7:00 AM to 7:00 PM •Monday, September 27 through Friday, October 1, 7:00 AM to 7:00 PM

Construction is ongoing at station and layover sites and along the railroad right-of-way from Middleborough to New Bedford.

Daytime Work on Fall River Secondary

Location of Work: •Adams Lane, Berkley •Richmond Road to Forge Road, Assonet •Freetown Station site, 161 South Main Street, Assonet •Collins Street, Fall River •Weaver’s Cove Layover Facility, 2680 North Main Street, Fall River •Fall River Depot site, 825 Davol Street, Fall River •Fall River Secondary Line railroad right-of-way

Dates/Hours of Work: •Monday, September 20 through Sunday, September 26, 7:00 AM to 7:00 PM •Monday, September 27 through Friday, October 1, 7:00 AM to 7:00 PM

Construction is ongoing at station and layover sites and along the railroad right-of-way from Berkley to Fall River.

Overnight Transportation of Soils to Assonet and Weaver’s Cove Site in Fall River

To prepare for overnight track work, the contractor will export material by truck off of the railroad right-of-way to designated stockpile locations in Assonet and the Weaver’s Cove Layover Facility site in Fall River. While every effort will be made to minimize trucking outside the hours of 7:00 AM to 7:00 PM, additional overnight trucking is anticipated in order to complete the work.

Location of Work: •Construction Yard, 11 Campanelli Drive, Assonet •Weaver’s Cove Layover Facility, 2680 North Main Street, Fall River

Dates/Hours of Work: Overnight Wednesday, September 29, Thursday, September 30 and Friday, October 1, 7:00 PM to 7:00 AM

Overnight and Daytime Transportation of Soils to Middleborough and Freetown Station Sites

Soils excavated from work along the Middleborough Secondary and New Bedford Mainline will be transported by truck to the new Middleborough Station site.

Location of Work: New Middleborough Station site, 161 South Main Street, Middleborough

Dates/Hours of Work: Friday, September 24, 7:00 PM to 7:00 AM; Saturday, September 25 and Sunday, September 26, 7:00 AM to 7:00 PM

Soils excavated from work in Taunton (East Taunton Station, Cotley Junction, and Galleria Mall area) and New Bedford (Church Street area) are being transported by truck to the Freetown Station site.

Location of Work: Freetown Station site, 161 South Main Street, Assonet

Dates/Hours of Work: Ongoing to end of September, 7:00 AM to 7:00 PM

The schedule for this infrastructure project is weather dependent and subject to change without notice.

Advertisement
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Trending

Copyright © 2017 Fall River Reporter

Translate »