Third Street garage repairs $2.5 million over budget, Coogan says

Also available in Português / Español / ខ្មែរ (Cambodian)

FALL RIVER ─ Mayor Paul Coogan confirmed Friday that the project to rehabilitate the Third Street parking garage, originally estimated at $6.5 million, is about $2.5 million over budget and three months behind schedule. That brings the total cost to about $9 million.

Coogan named two causes for the overrun. The first is that repairs to the four-level structure in 2017, made by its owner at the time, the Fall River Redevelopment Authority, didn’t last.

“It didn’t hold up as well as it should have to still be effective,” Coogan said.

At the time, local firm Starck Architects found the garage heavily compromised, especially on the top two decks.

The Third Street and Pearl Street garages have both deteriorated badly. Years of deferred maintenance and road salt in the winter have corroded the reinforcing steel in both.

The city’s building inspector issued a cease-and-desist order closing the top two levels of the Third Street garage. That cut it from 415 spaces to 200.

In 2019, the city took back ownership of both garages. The Pearl Street garage also needs millions of dollars in repairs, and its sale to local developer James Karam, the only bidder and the holder of a 2013 lease on the garage, is pending.

The second cause is that conditions turned out worse than expected once crews opened up sections of the garage.

Advertisement

Engineering firm Tighe & Bond, which assessed both garages in 2024 and is overseeing the project, originally scoped about 16,000 square feet of repairs. Coogan said the structural problems found since then have pushed that to about 19,000 square feet.

Next steps

The Third Street garage closed in July for the work, which was supposed to wrap up by the end of September. That deadline slipped to October and then again to mid-December.

The closure has temporarily displaced U.S. Postal Service vehicles and a few dozen city employees who park there.

Coogan said the garage will partially reopen in December with the upper decks still closed, leaving 174 spaces available through the winter. In the spring, the city will go out to bid for the roughly $2.5 million in additional work on the top decks.

Coogan said he has been meeting with city councilors to brief them on the overruns.

The City Council Committee on Real Estate, Facilities and Housing will meet Tuesday, Nov. 17, at 5 p.m. to discuss both garages, including the proposed sale of the Pearl Street garage for just over $1 million. The City Council must approve the sale, which has a late-December deadline.

The committee has already begun discussing the delays at the Third Street garage, but the $2.5 million overrun has not yet come up.