Community
MassDOT issues update on work taking place on South Coast Rail
MassDOT has issued an update on the work taking place concerning the South Coast Rail.
Fencing Installation: Middleborough, Lakeville, Raynham, Taunton, Berkley, Assonet
Location of work: •Installation of fencing along the Middleborough Secondary Line railroad right-of-way at locations between Route 140 in Taunton and the new Middleborough Station site (161 South Main Street, Middleborough) •Installation of fencing along the Fall River Secondary Line railroad right-of-way at locations between Myricks Street in Taunton and Beechwood Road in Assonet
Dates/Hours of Work: Monday through Friday, 7:00 AM to 7:00 PM
The MBTA’s contractor will begin installing fencing at locations along the Middleborough Secondary Line and Fall River Secondary Line railroad right of way.
Generally, fencing is placed in areas where it will enhance safety and minimize trespassing on the railroad right-of-way. Abutters to the railroad may see orange stakes marking survey boundaries and will notice crews working in the railroad right-of-way to install this fencing. In some locations limited tree and brush clearing may be needed to facilitate this work. The typical MBTA fencing that will be installed is 6-foot-tall chain link fencing. Fencing will be set on the MBTA’s property line.
Berkley: Railroad Access at Cotley Street
Location of work: Cotley Street in Berkley
Dates/Hours of Work: Please note that the contractor will be using Cotley Street to access the right-of-way for various work activities. This access will be primarily used during the daytime (7:00 AM-7:00 PM) but will also be used 24-hours/day during some activities.
Berkley: Railroad Work at Myricks Street
Location of work: Myricks Street in Berkley
Dates/Hours of Work: Monday through Saturday, 7:00 AM to 7:00 PM
Please note that although regular daytime construction hours begin at 7:00 AM, abutters may notice crews arriving at the construction sites prior to this time.
Currently, activity in the area includes conduit work, drainage work, and grubbing and roadbed prep work for the spring.
Daytime Work on Middleborough Secondary and New Bedford Main Line
Location of Work: •New Middleborough Station site, 161 South Main Street, Middleborough •East Taunton Station site, 1141 County Street, Taunton •Wamsutta Layover Facility site, 217 Herman Melville Boulevard, New Bedford •Church Street Station site, 387 Church Street, New Bedford • New Bedford Station Site, Acushnet Avenue (at Whale’s Tooth Parking Lot), New Bedford •Middleborough Secondary and New Bedford Main Line right-of-way
Dates/Hours of Work: •February 22 through Friday, February 25, 7:00 AM to 7:00 PM (No work Monday, February 21 for holiday)
Please note that although regular daytime construction hours begin at 7:00 AM, abutters may notice crews arriving at the construction sites prior to this time.
Construction is ongoing at station and layover sites and along the railroad right-of-way from Middleborough to New Bedford.
Daytime Work on Fall River Secondary Line
Location of work: •Adams Lane, Berkley •Freetown Station site, 161 South Main Street, Assonet •Weaver’s Cove Layover Facility, 2680 North Main Street, Fall River •Turner Street Railroad Bridge, Fall River •Fall River Depot site, 825 Davol Street, Fall River •Fall River Secondary Line railroad right-of-way
Dates/Hours of Work: •Tuesday, February 22 through Friday, February 25, 7:00 AM to 7:00 PM (No work Monday, February 21 for holiday)
Please note that although regular daytime construction hours begin at 7:00 AM, abutters may notice crews arriving at the construction sites prior to this time.
Construction is ongoing at station and layover sites and along the railroad right-of-way from Berkley to Fall River.
Overnight and Daytime Transportation of Soils to Freetown and Weaver’s Cove Sites
Please note that soils excavated from the railroad right-of-way during the above work are typically transported during the day and may be transported overnight by truck to the designated project sites in Freetown and Fall River where the soils will be stockpiled and spread.
Location of work: •Freetown Station Site, 161 South Main Street, Assonet •Weaver’s Cove Layover Facility, 2680 North Main Street, Fall River
Dates/Hours of Work: •Regular daytime hours 7:00 AM to 7:00 PM •Overnight as necessary, 7:00 PM to 7:00 AM
-
Community7 years ago
National Shrine of La Salette Festival of Lights 2017 set to begin
-
Community6 years ago
Massachusetts State Police looking for good home for retired dogs
-
Crime7 years ago
Fall River ranked most dangerous city in Massachusetts according to report
-
latest7 years ago
Durfee student allegedly overdoses on marijuana
-
Community6 years ago
Video of Fall River Police goes viral
-
Causes6 years ago
Missing Fall River woman found deceased
-
Crime7 years ago
Fall River Police add names to most wanted list
-
Causes7 years ago
Fall River teenager reported missing has been found
You must be logged in to post a comment Login