Cost of New Durfee and cost to Fall River announced

Massachusetts School Building Authority met with Fall River officials today to iron out the official cost of a new Durfee High School and how much of that cost would be put on the city of Fall River.

Published

on

The Massachusetts School Building Authority met with Fall River officials today to iron out the official cost of a new Durfee High School and how much of that cost would be put on the city of Fall River.

The draft agreement states that the MSBA, pending Board of Directors approval, agree on a total cost of the project at $263,496,000.

The agreement also states that Fall River’s tentative share is $98.5 million (37.5 percent).

The final date of MSBA approval is February 14th.

Officials will be attending a Fall River City Council meeting to supply more details.